For the purposes of building a new gas boiler house with a steam production capacity of 3×50 t/h, the following services were performed:
- mechanical, civil and plumbing project of connecting pipelines between the new boiler house and current sources and future consumers (basic design, main project and detailed design)
- Nostrification of the foreign basic and main design of the gas boiler house (mechanical-technological, civil and architectural, electrical and automation)
- Revision of the main project of the gas boiler facility (mechanical-technological, civil and architectural, electrical and automation)